Anniston, AL – Jackson Hodges, Anniston Public Relations Director, has announced that improvements to crosswalks are scheduled to be made in the coming month, at intersection at 11th Street and Noble Street. The work will begin as follows:


  • The Week One – 6/5/23 6/9/23


  • Week 2 6/12/23 – 6/16/23


  • week 4 from 6/26/23 to 6/30/23

The work on the crosswalk that is colored with blue is scheduled to begin, from June 6th until June 9th. The crosswalk will be colored in green will be completed between June 12th and the 16th of June. The two Noble Street crosswalks, colored in red, will be carried out between June 26th and June 30th.

During these weeks in each of these weeks, the crossings listed for work will be shut. This means that traffic won’t be able to travel through the designated crossing for that week.